The contractor for the Red Bluff Recreation Area project is progressing, but wet spring weather made it especially difficult for the crews. Â
Here are some highlights from a June 2 visit to Red Bluff.
The campsite spurs in the new North Loop have been shaped and a layer of base rock has been added. Some grading work continues around the sites. Â
Some work on drainage ditches and culverts has been completed.
The old asphalt on the Pines Overlook road has been removed and new drainage ditches and culverts have been installed. Â